1. A project manager is in a projectized organization managing a particular project. A department manager
has repeatedly requested a change to the scope of the project which was previously denied. The project is
currently behind schedule. Which of the following would be the BEST way to deal with the managers
repeated request?
A. Request the manager fill out a formal request for the change and file it with the project management
office.
B. Have a team member meet with the manager so the project can stay on schedule.
C. Ask the project sponsor to respond to the department manager.
D. Implement the change as requested by the manager and inform the project sponsor.
Answer: C
2. Which of the following is the purpose of a Pareto diagram?
A. To show the sequence in which work will be performed
B. To create the process that will complete the project
C. To determine the critical path
D. To direct team efforts to the areas that will have the most impact
Answer: D
3. Who has the MOST influence over project decisions?
A. Project team members
B. End users
C. Key stakeholders
D. Project manager
Answer: C